Cartersville Mission Critical Project
Overview
Hyperscale Data Center Development
Multi-phase mission critical project in Cartersville, GA on 1500 cares. The data center company intends to invest $772 million in the campus. The first phase of the project is set to complete in Q2 2026, with continued build-out to 2046.
Project Description / Details
- Phase 1(current started in 2024): 180 acres
- Phase 2 (timbered): 250 acres
- Overall site acreage: 2,000 acres
- 10-year project: 2035 estimated completion
BACK TO PROJECTS
Additional Details
Service Type: Mission Critical
Location: Cartersville, Georgia
Additional Project Details:
- Acreage: 430
- Earthwork: 1,174,070+ CY
- Rock: 28,640 CY
- Blasting: 35,200 CY
- Storm Pipe: 16,610 LF
- Sanitary: 1,890 LF
- Water (Dom and Fire): 6,240 LF
- Walls: 15,720 SF