Hampton Data Center

Overview

133-Acre Data Center Campus Approved in Hampton, Georgia.

Hampton officials have granted a conditional use permit for a 133-acre data center campus north of Georgia 20 at McDonough Street. This development, part of the larger 900-acre Henderson Farms project, marks the first data center in Henry County. ​

Project Description / Details

Project Highlights:

Campus Composition: Three buildings, each approximately 195,000 sq ft, along with an electrical substation.​
Data Center Dynamics

Sustainability Initiatives: Plans include a hydroponic farm and training facility in collaboration with the University of Georgia.​
Data Center Dynamics

Community Commitments: The developer will donate produce to non-profits, allocate land for a city park, contribute $75,000 to Hampton, implement green roofing, and conduct a noise impact study.​

BACK TO PROJECTS

Additional Details

Service Type: Mission Critical

Location: Hampton, Georgia

Additional Project Details:

  • Acreage: 133 acres
  • Earthwork: 285,920 CY
  • Rock: 24,680 CY
  • Blasting: 31,500 CY
  • Storm Pipe: 4,850 LF
  • Sanitary: 1,690 LF
  • Water (Dom and Fire): 5,720 LF
  • Walls: 13,450 SF